Trial Operation of Xinjiang Kingho Coal-to-Gas Project in June

來源: Xinjiang Daily
編輯: 阿勇
發布時間: 2013-05-31
訪問量: 4863

Reported by Chen Qiangwei, a correspondent from Xinjiang Daily News: On April 28, at the construction site of Phase I Coal Made-gas Project (5.5 Billion Cubic Meters/Year) of XinJiang Kingho Energy Group, some workers are busying with preparation of filling the catalyst for a smooth production. “All the works of this project have been going through well, and it is expected to put into production in the second half of this year”, said by Xu Zhong, the Party Secretary and General Manager of Xinjiang Kingho Energy Group.
    As the first modern coal and chemical project approved on state-level, Coal-to-Gas project (5.5 Billion Cubic Meter/Year) of Xinjiang Kingho has received great attention to its progress. “Up to now, the entire project have been mechanically completed, the power supply, water supply, coal supply and thermal power supply facilities have been under operation, 8 gasifiers have been successfully started, gas pipe lines have been ready for transmission, and it is planned to conduct linkage commisioning in June.” said by Xu Zhong.
    The Goal-made Gas project (5.5 Billion Cubic Meter/Year) of Xinjiang Kingho Energy Group locates at the Yidong Industrial Park of Yining County with a total investment amount over 30 billion Yuan. This project can create sales income of 12 billion Yuan, contributing taxes of 2.5 billion Yuan and more than 10,000 jobs directly or indirectly once it is up and running. It ranks NO.1 among the State Modeling Projects of Coal Fine Processing of the 12th Five-year Plan. It is the largest state-level demonstration project among the private enterprise projects in China.
    In the year of 2009, Xinjiang Kingho Energy Group Company Limited (hereafter referred as Xinjiang Kingho) settled in Xinjiang, and built the Kingho Recycling Economy Park targeted to realize the clean utilization of coal and to improve coal added value and develop a large coal-based natural gas industry system in Yining County.

The main structure construction of Phase I Coal Utilization Project (12 Million Tons/Year) invested by Xinjiang Kingho has been started in Sura Palance Industry Park recently. It was said that the project is a supporting project for the coal-to-gas project with an investment amount of 23.6 billion Yuan.” It has a positive demonstration effect on coal separation and clean and efficient utilization, and it is in line with the national industrial policies for priority industry planning.” indicated by Xu Zhong. In addition, Xinjiang Kingho is planning to construct a coal mining project of ten million tons to ensure the raw material supply for coal-to-gas project.

How to protect the natural environment of Xinjiang while accelerating the resource exploration is a concern worthy of provoking of all Xinjiang Kingho people. The recycling development model of “reduction, resource reuse, recycling” has been chosen by Xinjiang Kingho for protecting the environment. Advanced crushed coal pressure gasification technology in combination with low-temperature methanol cleansing were adopted in the production procedure of coal-to-gas proejct(5.5 Billion Cubic Meters/Year), which greatly reduced pollutant emissions. The polluted water would be only be diverted to the recycled water system and reused after going through sewage treatment unit and reaches level 1 standard, as to avoid the pollution from the waste water. 
  It was learnt that the investment amount of Xinjiang Kingho is up to 15.1 billion Yuan including the used 12.2 billion Yuan for coal-to-gas project and related supporting projects in Xinjiang in the past three years.
  “2013 is a critical year for Xinjiang Kingho to realize a new leap, and we have identified 2013 as the “Year of Coal-to-gas Production”, “Year of Increase the Output Capacity of Mining Area”, “Year of Coal Utilization Production”, “Year of Experiment of Tacheng Oil-sand Mine Large-scale Development”, addressed by Xu Zhong. Xinjiang Kingho Energy Group Company Limited plans to complete an investment of 5.2 billion Yuan in 2013.


    Meng Yongsheng (Vice President of Economics College of Xinjiang University of Finance and Economics)
    Many enterprises were attracted by Xinjiang after the Central Xinjiang Working Conference, Kingho Group was actually one of them. The coal-to-gas modeling project (5.5 Billion Cubic Meters) of Kingho is a landmark energy development project, having a significant meaning in our region. The project construction would do a favor to improve the demonstration layer and level of the local coal-to-gas technology, promote the shifting of coal resources to economic advantages. It has significant meaning to make use of the local resource advantage to complement the shortage of oil and gas nationwide, to secure national energy safety, and to promote the regional economic and social development.
    The project construction would do a favor to improve the demonstration layer and level of the local coal-to-gas technology, promote the shifting of coal resources to economic advantages. It has significant meaning to make use of the local resource advantage to complement the shortage of oil and gas nationwide, to secure national energy safety, and to promote the regional economic and social development.

Events Review
1. March, 2009, Xinjiang Kingho Energy Group was founded.

2. May 6,2009, Foundation Laying of Xinjiang Kingho Coal and Chemical Recycling Economy Industry Zone
3. Dec. 30, 2011, the registered capital of Xinjiang Kingho Energy Group Co., Ltd. was increa to 3 billion Yuan China as Kingho Energy Group Company Limited invested the 5.5 billion Cubic Meters Coal-to-gas Project of Xinjiang Kingho Group.
4. July, 2012, 5.5 billion Cubic Meters Coal-to-gas Project was approved by the National Development and Reform Commission, ranking the top 1 of the State Modeling Projects of Coal Fine Processing of the 12th Five –year Plan. It is the first modern Coal and Chemical project approved by State in autonomous region.
5. Nov. 2012, phase 1 of coal-to-gas project has accomplished mechanical completion, and the trial operation is planned in June, 2013. 

主站蜘蛛池模板: 国产欧美成人精品第二区 | 久久久久久人妻精品一区二区三区 | 国产精品色网 | 在线看一级毛片免费视频播放 | 中国xxxxxxxxx88 | 欧美熟妇的性裸交 | 三上悠亚福利一区二区 | 性亚洲videofree高清极品 | H无码精品动漫在线观看导航 | 日韩精品无码一本二本三本色 | 高清偷自拍亚洲精品三区 | 性虎精品无码AV导航 | 少妇愉情理仑片高潮 | 国产强奷女交警在线播放 | 久久久久久久婷婷 | 蜜芽亚洲AV无码一区二区三区 | 日韩精品一卡2卡3卡4卡新区视频 | 67PAO国产成视频永久免费 | 日本饥渴人妻欲求不满 | 免费观看国产女人高潮视频 | 免费A片看黄网站WWW | 亚洲尺码欧洲尺码有哪些品牌好 | 国产剧情av一区二区三区在线观看 | 性一交一无一伦一精一品 | 中文日产无乱码av在线观 | 久久九九国产精品怡红院 | 蜜臀av999无码精品国产专区 | 亚洲精品无码鲁网午夜 | www毛片| 成人免费看黄网站yyy456 | 人妻丰满熟妇av无码区 | 国产精品久久久久久久久久久久人四虎 | 国产av丝袜一区二区三区 | 久艹视频在线观看 | 久久精品国产亚洲AV网站 | 啊啊啊啊啊用力操 | 免费精品国偷自产在线青年 | 国产一区二区三区免费高清在线播放 | 好吊在线观看 | 三年片大全免费观看 | 大香伊蕉在人线国产av |